27 Trains to Reach Pakistan Under Orange Line Project

Posted in : Local News

(added few years ago!)

Ever since the establishment of CPEC, China has been of great help to Pakistan, both economically and environmentally. Many power and infrastructure projects have been introduced in the country under the $62 billion agreement. Specifically, while talking considering the transportation projects initiated under CPEG, the first-priority is given to Orange Line Metro Train Project, Lahore worth Rs. 1.78 billion. This project consists of 27 trains in total out of which 17 trains have already reached the town. By The Next Week, All 27 Trains For The Orange Line Metro Train Project Will Reach Lahore. According to the Punjab Chief Minister’s Adviser and OLMT Steering Committee Chairman Khawaja Ahmad Hassaan, almost 84% of the work has been completed, and for the remaining, the Chinese workers and the local citizens are working hard to complete it.

27 Trains to Reach Pakistan Under Orange Line Project

He confirmed the news of trains reaching Pakistan in the coming week, and also updated the media on the weekly progress of this project.

He also enlightened everyone about the progress on other projects, including;

- Package-I Dera Gujjaran, Grand Trunk Road to Chauburji = 89.5%
- Package-II Chauburji to Ali Town) = 75%
- Stabling Yard near Ali Town = 85%
- Depot near Dera Gujran = 86%

Salman Hafeez, General Manager of National Engineering Services Pakistan (NESPAK), reported that 40% electrical and mechanical work is done and 84% civil work is completed.

27 Trains to Reach Pakistan Under Orange Line Project

He told the media that:

“AFTER SUPREME COURT RESTRAINING ORDER, NOW THE WORKAROUND SHALIMAR GARDEN, GHULABI BAGH AND BUDHU’S TOMB ON GRAND TRUNK ROAD ALONG WITH LAKSHMI BUILDING ON MECLEOD ROAD IS IN FULL MOTION. PILING WORK IS DONE. OUT OF TOTAL 41 PEARS, 19 ARE CONSTRUCTED. IN THESE AREAS, 38 TRANSOMS AND 90 U-TUB GIRDERS WILL BE INTRODUCED. ON PACKAGE-I, THERE ARE 13 METRO STATIONS AND IN 12 STATIONS 85% WORK IS DONE. ON PACKAGE-II OUT OF 806 U-TUBS, 802 WERE PRECAST”.

The engineer assured that the team is working on Supreme Court’s order of preserving and safeguarding the historical places. Orange Line in a project that will facilitate the commuters in Lahore by making transportation easier for them.

Blog post Written by Umaima Nadeem and you can visit the original article at https://www.brandsynario.com/

Tags : Trains, Reach, Pakistan, Orange, Line, Project, Supreme, Court, Packages, CPEC, China, Economically, Chairman, Khawaja Ahmad Hassaan, Chinese, Workers, Local, Citizen, Project, Lahore, Transportation

Related Posts

» Boxer Amir Khan declines offer to join Pakistani politics

» Jannat Mirza says she was relieved after TikTok ban in Pakistan was lifted

» Pakistan to carry out 50,000 tests per day starting next week, says NDMA chairman

» Prime Minister finance adviser says bad days gone, Pakistan moving towards economic stability

» Alleged in Money Laundering Sofia Mirza Called FIA Cyber Crime of Help

» Pakistan will never leave its Kashmiri brethren alone: COAS

» Black Day being observed across Pakistan

» 'Clean Karachi' drive gets underway

(added few years ago!) / 1667 views

Comments (0)

Search this blog..

Top Stories of the week

Existing Users Login
User ID
Password
 
 
Join Now / Forgot Password

also you can..
Login with Facebook